Overview of plant construction progress

Stockpile feed conveyor, crusher area and ROM pad retaining wall

Crusher area construction works

Mill feed conveyor

Mill feed conveyor take up tower

SAG mill foundations and platform progress



Thickener and flotation tanks, float tails pumps



Float tank dart valve controllers

Flotation thickener construction progress



CIL tank construction progress


HV substation work progress

Offices and plant buildings