January 2011
Overview of plant construction progress
Stockpile feed conveyor, crusher area and ROM pad retaining wall
Crusher area construction works
Mill feed conveyor
Mill feed conveyor take up tower
SAG mill foundations and platform progress
.jpg)
Thickener and flotation tanks, float tails pumps
.jpg)
Float tank dart valve controllers
Flotation thickener construction progress
CIL tank construction progress
HV substation work progress
Offices and plant buildings